Maroma

Land & Entitlements Fact Sheet
Playa Maroma · Riviera Maya · Quintana Roo, Mexico
Land Composition

Two Titled Parcels, Unified Entitlement

The site comprises two contiguous parcels — La Ley del Monte (97.64 ha) and San Juan Maroma (17.41 ha) — totaling 1,150,524 m² with a single unified environmental resolution (DTU-BR) covering both.

Ley del MonteSan Juan MaromaTotal
Total Area (m²)976,394174,1311,150,524
Development Area290,772 m²60,045 m²350,817 m²
Development %29.78%34.48%30.49%
Conservation %70.22%65.52%69.51%
Authorized CUS

Change of Land Use by Vegetation

SEMARNAT authorized the change of land use on 342,481 m² (34.25 ha) of forest land, broken down by vegetation type across both parcels.

Vegetation TypeLey del MonteSan Juan MaromaTotal
Coastal Dune (Matorral)10,85052,23063,081 m²
Low Deciduous Forest272,0587,343279,401 m²
Total CUS282,90859,574342,481 m²

Source: DTU-BR Expediente 23QR2016T0012 — Oficio SGPA/DGIRA/DG/02306.

Master Plan

Development Zoning

Zones A1–A10 designate hospitality, residential, amenity, conservation and infrastructure areas across the site. Maximum authorized density: 10 keys per hectare.

Plan Maestro — Zoning

Master Plan — Zoning Layout — source: DTU-BR documentation.

Environmental Authorization

DTU-BR — Unified Resolution

The DTU-BR (Documento Técnico Unificado, modalidad B-Regional) is a unified federal instrument that resolves both the Environmental Impact Assessment and the Forest Land-Use Change authorization in a single proceeding — eliminating the need for separate filings and providing a consolidated entitlement that is rare and highly valuable for coastal development in Quintana Roo.

Permit Type
DTU-BR — Unified Environmental & Forest Land-Use Authorization
Authority
SEMARNAT — DGIRA
Resolution
SGPA/DGIRA/DG/02306
Issue Date
March 28, 2017
Status
AUTHORIZED — Conditional
Expediente
23QR2016T0012
Entity
Amikoo Resort and Entertainment, S.A. de C.V.
Max Density
10 rooms per hectare
FFM Deposit
$9,364,045 MXN (forestry compensation)
Construction Extension

6-Year Extension Granted

Extension Oficio
SRA/DGIRA/DG-03918-23
Granted
October 11, 2023
New Deadline
March 30, 2029
Operations
50 years from completion
Modification #
First (of two permitted)

Original 6-year construction window (2017–2023) was extended for an additional 6 years through March 2029. Extension was requested January 2023 and granted October 2023 by DGIRA, citing pandemic-related delays. All original terms and conditionants remain fully in force under PROFEPA oversight.

Mar 2017
DTU-BR
Approved
Jan 2023
Extension
Requested
Oct 2023
Extension
Granted
Apr 2026
Today
Mar 2029
Construction
Deadline
Maroma — Land & Entitlements Fact Sheet · April 2026 Strictly Confidential · For Discussion Purposes Only